Apply for a building permit for the construction of a plant using the simplified procedure

Description

Before you are allowed to build a plant that requires a permit, you need a building permit.

To do this, submit a building application to the responsible lower building supervisory authority. For some projects, you must commission a design author (e.g. civil engineer or architect) who is authorized to submit building documents.

In your application, you can also request whether you want to make use of the simplified procedure. In this case, for example, the authority does not check building planning regulations.

  • Complete building application
  • Construction project is in accordance with public law regulations
  • If not, deviations can be requested and justified with the building application. Thebuilding supervisory authority checks whether the deviations can be approved.
  • Building application (via online service or publicly published form),
  • Excerpt from the official real estate cadastre,
  • Site plan
  • construction drawings,
  • Specifications.

In addition, where they are to be submitted:

  • Proof of stability,
  • fire safety certificate,
  • Information on the secured development.

Please ask the lower building supervisory authority responsible for you which documents you need to submit for your specific construction project.

at least 50 €

Fees for a building permit for every €500 or part thereof of the chargeable construction value = €5

Fees depend on the following factors:

  • Effort for the examination of the building permit
  • Expected costs of construction

You must start construction within 3 years when you get the building permit.

You may then interrupt the construction work for a maximum of 1 year.

You can have the building permit extended for 1 year.

The building supervisory authority will decide on your building application within 3 months. The period begins on the confirmed date of receipt.

In principle, your application is automatically approved if you have not received a decision from the building supervisory authority after 3 months.

Contradiction

Action before an administrative court of the State of Saxony-Anhalt

lower building supervisory authority

Forms available: Yes

Written form required: No

Informal application possible: No

Personal appearance required: No

Online services available: Yes

You can apply for a building permit for the construction of a plant via online service or in writing.

When using the form, proceed as follows:

  • Fill out the form.
  • Add the required building templates.
  • Submit the application documents to the responsible lower building supervisory authority.
  • If necessary, the lower building supervisory authority will ask you to pay a fee in advance.
  • Make the advance payment.
  • If documents are missing or there are other ambiguities, you will be asked to correct them.
  • In this case, submit the missing or adapted documentation and/or clarification.
  • The lower building supervisory authority will examine your application and involve the competent authorities whose involvement or consultation is necessary.
  • You will then receive the building permit and a fee notice.
  • Pay the fees.

If you have a building permit, you must submit a notification of the start of construction to the lower building supervisory authority at least one week before the start of construction of the facility.

Ministry of Infrastructure and Digital Saxony-Anhalt

The text was automatically translated based on the German content.

Authority
Landkreis Wittenberg - Fachliche Bauaufsicht (Bauanträge, Vorbescheide ...)
Breitscheidstraße 3
06886 Lutherstadt Wittenberg
Breitscheidstraße 4
06886 Lutherstadt Wittenberg
03491 806-2850
03491 806-2890

Employee

03491 806-2819
03491 806-2890
A2-24

03491 806-2816
03491 806-2890
A2-30