View commissioning of low-frequency systems
Description
As an operator of a low-frequency system with a nominal voltage of 110 KV or more or a direct current system, you are obliged to notify the competent authority of this before commissioning or a significant change.
The competent authority shall examine the notification and record the installation in its plant register.
The prerequisite is that
- the installation is located on a plot of land in the area of a development plan or within a contiguous built-up district or on a plot of land developed with residential buildings in the outdoor area or crosses such land,
- the plant or its substantial modification does not require a permit, planning approval or other official decision that takes into account the interests of immission control.
- Display with the data relevant for the system
- Site plan
The notification shall be submitted to the competent authority at least two weeks before the installation is put into operation or before any significant change to the installation.
This administrative service does not constitute an administrative act. For this reason, there is no remedy.
Contact the State Administration Office.
The notification shall be submitted in writing by post or electronically to the competent authority.