Applying for a partial building permit for the construction of a system
Description
If you have applied for planning permission and would like to start building individual sections of the building before planning permission is granted, you will need partial planning permission for this construction work.
To do this, you submit an application for partial building permission to the responsible lower building supervisory authority. In the application, you specify which individual components or construction phases you would like to start with before the building permit is granted.
You receive a partial building permit:
- if the building application is complete with regard to the building measures applied for partial building permission
- the described building project complies with the public law regulations
- Application (digital or written)
If not yet submitted with the building application:
- Extract from the official real estate map
- site plan
- Construction drawings
- Building description
Please contact your local building supervisory authority to find out which documents you need to submit for your specific building project.
Fee: 50,00 - 1500,00 EURPayment in advance: nohttps://www.landesrecht.sachsen-anhalt.de/bsst/searchThe fees depend on the following factors: - Expenditure for the examination of the partial building permit - Expected costs of construction The fees for the partial building permit are to be offset against the fee for the building permit if they exceed €150.
none
Processing Time: 0 - 3 MonthsThe building supervisory authority decides on the building application within 3 months. The deadline begins with the confirmed date of receipt. Exception: The building supervisory authority can extend the deadline by a maximum of 2 months if there is an important reason. If the deadline is extended, you will be informed, stating the reasons and the expected date of the decision.
Contradiction
Lower building supervisory authority
Forms/online services available: yes
Informal application possible: yes
Personal appearance necessary: no
You can apply for a partial building permit for the construction of a system digitally or in writing.
If you apply in writing, proceed as follows:
- Submit the application and state in it which building application your application for partial building permission relates to and which construction measures it covers.
- Attach the required building documents.
- Submit the application documents to the responsible lower building supervisory authority.
- If necessary, the lower building supervisory authority will ask you to make an advance fee payment.
- Make the advance payment.
- If documents are missing or if there are other ambiguities, you will be asked to complete or rectify them.
If you have a partial building permit, you must submit a notice of commencement of construction work to the lower building supervisory authority at least one week before the start of construction work.
- Information from the Ministry of Infrastructure and Digital Affairs - Planning permission
Remark: When planning and approving a building project, a number of building regulations and planning regulations must be observed.
- Overview of public building law
- Overview of the building supervisory authorities in Saxony-Anhalt
Remark: You can find the building supervisory authority responsible for your building project here.
- § Section 73 Building Regulations of the State of Saxony-Anhalt (BauO LSA)
- Ordinance on building documents and notifications to building authorities (Bauvorlagenverordnung BauVorlVO)
- Building Fees Ordinance (BauGVO)
- Administrative Regulation Technical Building Regulations (VV TB)
- Annex for Administrative Regulation Technical Building Regulations (VV TB)
Ministry of Infrastructure and Digital Affairs of the State of Saxony-Anhalt
15.05.2023
The text was automatically translated based on the German content.