Show start of construction
Description
Before you start a construction project that requires a permit or is exempt from approval, you must notify this one week in advance. You can submit this notification of the start of construction in writing or online.
This also applies if you have interrupted the construction work for more than 3 months and now want to resume it.
If your construction project is exempt from procedures, this notification is not necessary.
- You have a building permit or permit exemption
Notification of the start of construction (digital or written)
There are no costs.
At least one week before the start of construction
This also applies to the resumption of construction work if you have interrupted construction work for more than 3 months.
Lower Building Inspectorate
Form available: yes
Online procedure possible: yes
Written form required: yes
Personal appearance required: no
Submit the notification of the start of construction to the building supervisory authority. You can submit the notification of the start of construction online or in writing.
Pay attention to the deadlines.
The lower building supervisory authority then checks whether the conditions for the start of the construction project are met.
Feedback from the authority is not necessary.
You can start construction within 3 months from the indicated start of construction. If the building inspectorate decrees otherwise, you need to pay attention to this.
If you do not submit the notification of the start of construction or do not submit it in time, this can be punished as an administrative offense. In this case, you may have to pay a fine
Permit, building templates and structural engineering evidence must be available at the construction site from the start of construction.