Apply for approval in the simplified procedure for an installation in accordance with the BImSchG
Description
Permits for installations of a certain type or scope can be issued in a simplified procedure. In these cases, the procedure is carried out without public participation.
You will receive a permit if you fulfill the obligations under the Federal Immission Control Act and the project does not conflict with any other public law regulations.
The cases in which a simplified approval procedure is possible can be found in the legal basis.
- You must prove that you will comply with the obligations of the Federal Immission Control Act when constructing and operating a plant.
- No other public law regulations or occupational health and safety concerns stand in the way of the project.
- main application
- Required drawings, plans or expert opinions
- Explanatory notes on the installation
- Other documents (if necessary, ask the competent authority)
Before construction of the plant.
- Objection
- Further information on how to lodge an appeal can be found in the notification.
- Complaint
If you run a business that is subject to mining supervision, please contact the State Office for Geology and Mining (LAGB).
There are no indications or special features.
- § Section 19 of the Act on Protection against Harmful Environmental Impacts from Air Pollution, Noise, Vibrations and Similar Processes (Federal Immission Control Act BImSchG)
- Fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Installations Requiring a Permit - 4. BImSchV) Annex 1
Federal Ministry for the Environment, Nature Conservation, Nuclear Safety and Consumer Protection (BMUV)
18.07.2023