Applying for planning permission for the change of use of a facility using the simplified procedure

Description

Before you are allowed to change the use of a facility that requires approval, you need a change of use permit (building permit). In your application, you can also apply to use the simplified procedure. In this case, the authorities will not check building planning regulations, for example.

To do this, you submit a building application to the responsible lower building supervisory authority. As a rule, you must commission an authorized draftsman - for example a civil engineer or architect - for this.

In your application, you can also specify whether you wish to make use of a reduced inspection program.

  • The building project complies with public law regulations
  • If not, you can apply for and justify deviations with the building application
  • Building application (via online service or form),
  • Extract from the official real estate register,
  • site plan,
  • construction drawings,
  • building description.

If they are to be submitted, also:

  • Proof of stability,
  • fire protection certificate,
  • Information on the secured development.

Please contact your local building authority to find out which documents you need to submit for your specific building project.

at least 50 €

Fees for a building permit for every € 500 or part thereof of the chargeable construction value = € 5

The fees depend on the following factors

  • Expenditure for the examination of the building permit
  • Expected costs of construction
  • You must start construction work within 3 years of receiving planning permission.
  • You may then interrupt the construction work for a maximum of 1 year.
  • You can have the building permit extended for 1 year.

The building supervisory authority will decide on your building application within 3 months. The deadline begins with the confirmed date of receipt.

In principle, your application is automatically approved if you have not received a decision from the building supervisory authority after 3 months.

Objection

Action before an administrative court of the state of Saxony-Anhalt

Lower building supervisory authority

You can apply for a building permit for the change of use of a facility electronically via the online service or in writing in paper form using the form.

Proceed as follows when using the form:

  • Complete the form.
  • Attach the required building documents.
  • Submit the application documents to the responsible lower building supervisory authority.
  • If necessary, the lower building supervisory authority will ask you to make an advance fee payment.
  • Make the advance payment.
  • If documents are missing or there are other ambiguities, you will be asked to rectify these.
  • In this case, submit the missing or amended documents and/or the clarification.
  • The lower building supervisory authority will review your application and involve the relevant authorities whose participation or consultation is required.
  • You will then receive the building permit and a notification of fees.
  • Pay the fees.

If you have a building permit, you must submit a notice of commencement of construction to the lower building supervisory authority at least one week before the change of use of the facility begins.

Ministry of Infrastructure and Digital Affairs Saxony-Anhalt