Apply for a partial building permit for the modification of a plant

Description

You need a partial building permit if you want to start with the partial modification of facilities before the actual building permit.

To do this, submit an application for a partial building permit to the responsible lower building supervisory authority. In the application, you indicate for which parts of the structure you would like to start before the permit is granted. The partial building permit for the modification of a plant is subject to a fee.
 

You will receive a partial building permit for the modification of structural installations if:

  • the building application is complete with regard to the changes requested for the partial building permit, and
  • the public law regulations are complied with
     
  • Application (via online service or in writing)
  • If not already submitted for the building application:
    • Excerpt from the official property map
    • Site plan
    • Construction drawings
    • Specifications

Please ask the lower building supervisory authority responsible for you which documents you need to submit for your specific construction project.
 

The fees for the partial building permit are: 50 to 1,500 €.

The cost depends on the following factors:

  • Effort for the examination of the partial building permit
  • Expected costs of construction

 
The partial building permit fee will be deducted from the building permit fee if the partial building permit fee is higher than €150.
 

You must start construction work within 3 years if you receive the partial building permit.

You may then interrupt the construction work for a maximum of 1 year.

You can have the partial building permit extended for 1 year.
 

Processing Time: 0 - 3 Months
The period begins on the confirmed date of receipt. Exception: The building supervisory authority may extend the deadline by a maximum of 2 months if there is an important reason. If the deadline is extended, you will be informed, stating the reasons and the expected date of the decision.

You can file an objection.

Please contact the responsible lower building supervisory authority.

  • Forms/online services available: yes
  • Written form required: no
  • Informal application possible: yes
  • Personal appearance required: no
     

You can apply for a partial building permit for the modification of a plant via online service or in writing.

If you submit a written application, proceed as follows:

  • Submit the application and indicate in it which building application your application for partial building permit relates. Indicate which construction measures you would like to start early.
  • Add the required building templates.
  • Submit the application documents to the responsible lower building supervisory authority.
  • If necessary, the lower building supervisory authority will ask you to pay a fee in advance.
  • Make the advance payment.
  • If documents are missing or there are other ambiguities, you will be asked to eliminate these ambiguities.
  • In this case, submit the missing or adapted documents or clarification.
  • The lower building supervisory authority will examine your application and involve the competent authorities whose involvement or consultation is necessary.
  • You will then receive the notification of your application as well as a fee notice.
  • Pay the fees.
     

If you have a partial building permit, you must submit a notification of the start of construction to the lower building supervisory authority at least one week before the start of construction work.

At least 2 weeks before the start of use, you must submit a notification of the start of use to the lower building supervisory authority.
 

Ministry of Infrastructure and Digital Affairs of the State of Saxony-Anhalt

The text was automatically translated based on the German content.

Start your request directly online:

Authority
Landkreis Wittenberg - Fachliche Bauaufsicht (Bauanträge, Vorbescheide ...)
Breitscheidstraße 3
06886 Lutherstadt Wittenberg
Post Office Box 10 02 51
06886 Lutherstadt Wittenberg
Breitscheidstraße 4
06886 Lutherstadt Wittenberg
03491 806-2850
03491 806-2891

Consultation hours of the specialist services:

Tue 08:30 - 12:00
13:00 - 15:00
Thu 08:30 - 12:00
13:00 - 18:00

Information of the district of Wittenberg:

Mon 08:30 - 17:00
Tue 08:30 - 17:00
Wed 08:30 - 14:00
Thu 08:30 - 18:00
Fri 08:30 - 14:00

03491 806-2804
A2-14
Contact person for the urban area of Gräfenhainichen

Herr Michael Dorn

Function: SGl Structural fire protection
03491 806-2816
03491 806-2890
A2-30
SGl Structural fire protection

03491 806-2806
A2-16
Contact for the urban area of Lutherstadt Wittenberg

03491 806-2807
A2-23
Contact for the Zahna-Elster and Annaburg municipal area

Frau Ricarda Mählis

Function: Head of department
03491 806-2808
A2-24
Contact person for the city of Jessen (Elster)

03491 806-2809
A2-21
Contact for the urban areas of Coswig (Anhalt) and Oranienbaum-Wörlitz

03491 806-2811
A2-20
Contact person for the city of Kemberg

03491 806-2812
A2-20
Contact person for the urban area of Bad Schmiedeberg

03491 806-2813
A2-16